Key points of steel-plastic geogrid construction methods
- Categories:News
- Author:
- Origin:
- Time of issue:2021-12-30 11:38
- Views:
(Summary description)Steel-plastic geogrid construction method points 1, geogrid laying surface should be relatively flat, paving layer acceptance, in order to prevent longitudinal skew phenomenon, first according to the width of the paving layer in the white line or hanging line, you can start laying, and then use U-shaped nails to fix the end of the grid (4 nails per meter wide, uniform distance fixed).
Key points of steel-plastic geogrid construction methods
(Summary description)Steel-plastic geogrid construction method points 1, geogrid laying surface should be relatively flat, paving layer acceptance, in order to prevent longitudinal skew phenomenon, first according to the width of the paving layer in the white line or hanging line, you can start laying, and then use U-shaped nails to fix the end of the grid (4 nails per meter wide, uniform distance fixed).
- Categories:News
- Author:
- Origin:
- Time of issue:2021-12-30 11:38
- Views:
Key points of steel-plastic geogrid construction methods
1、The laying surface of the geogrid should be relatively flat, after the laying layer is accepted, in order to prevent the longitudinal skew phenomenon, first according to the width of the laying layer to draw a white line or hanging line, you can start laying, then use U-shaped nails to fix the end of the grating (4 nails per metre wide, even distance fixed).
2、After fixing the ends of the grid, use the laying machine or manual method to slowly pull the grid forward, every 10m long for manual straightening, until a roll of grid is finished, then lay the next roll, the operation is the same as before.
3、Paving: The length of the roll is used as the length of the section to be laid. After the section of the grating has been laid, the overall quality of laying is checked once again and then the next section is laid.
When laying the next section, the grating and grating to overlap a grid net distance for the lap length, and fixed with a tie line and then continue to lay two sections in the forward direction. And so on, with the same operational requirements as before.
Professional Road Construction Geosynthetics Manufacturer !

Add:9/F, building 1,Lane 925,Aksu South Road,Shanghai
Tel : 0086 21-61277300
Mobile:0086 189 1690 0619 (same number on whatsapp)
E-mail : info@uning.com.cn